    This picture is from our ongoing project in Derby, where we are constructing a large energy from waste plant for Interserve. The picture shows a pour on the Reception pit base slab which is formed 12m below ground level and contains over 1000m3 of concrete and more than 150t of reinforcement. The reception pit has 12m high in situ concrete walls and in the back ground you can see the RDF structure which also has in situ concrete walls being constructed at 12m high. The works are ongoing with completion of the main concrete structures expected in early 2016.